Continued post-live run support of the T24, ERP and RTGS (net settlement)
applications at HQ, Garki, Minna and Lagos branches
Established dedicated connection to the Extranet Gateway with all banks
and discount houses and commenced eFASS parallel run with all
The last 6 outstanding banks were trained on RTGS and prepared to join the
operational run
Conducted second round UAT for TIB (Retail and Trade Services) with banks
and select parastatals and further regression test on DFD module of T24
Finalised plans for the integration test of T24 and RTGS
Concluded refresher training for T24 and ERP trainers prior to training
users in roll-out branches. Concluded train-the-trainer for EMS Services
Contract awarded for link between NDIC and CBN for eFASS deployment
Concluded UAT and obtained stakeholders sign-off for Business Intelligence
modules of CPM
Concluded assessment of the Project EAGLES to determine realised benefits
and gaps
Issues:
Inability to pass debit entries, setting of head teller limits and
printing of day-end journals by office instead of by-user. Duplication of
paid instrument.
Inability to sweep balances on regular basis via standing orders.
Mandatory printing of advices for tellers.
Inability to validate BN status of staff.
Non-utilisation of some ERP modules: Purchase Order, Inventory, Training
Admin, Learning Management System due to absence of data
Revaluation of FX by Reserve Management division of FOD. Completion of
the update of HR policies and procedure manual and obtain COG’s approval
Non-utilisation of some ERP modules: Purchase Order, Inventory, Training
Admin, Learning Management due to absence of data
Review and revalidation of the Enterprise Scorecard by the Governor/COG
Establishing communication link between CBN and NDIC, OFI’s connection
to the eFASS system.
Integration of the IDMS solution with MICR to enable the new redesigned
processes
June
2006:
User Acceptance Test (UAT) of the RTGS-T24 interface was concluded and we
obtained users sign-off on the UAT of DFD module of T24.
Completed the set-up of approval hierarchy for the Purchases and Invoicing
(AP) module of oracle ERP application.
Conducted connectivity test to CBN’s Extranet Gateway for the 6
outstanding participants and also concluded training set-up for the RTGS
application.
Continued the monitoring of live-run of the RTGS net settlement module
Commenced end-user training for rollout of T24 & Oracle ERP applications
to outstanding CBN branches Oracle ERP. Obtain COG’s approval for completion
of the update of HR policies and procedure manual, IT policies for EMS
implementation
Commenced live-run of the policy and procedure manual module
Concluded UAT for the synchronization of directory services with oracle
ERP
Operational /parallel run is ongoing with the 25 banks and 5 discount
houses while live run will commence in Q3 2006
Issues
On T24 application, the systems’ inability to pass debit entries and the
setting
of head teller limits.
Inability to print Day-End journals by office instead of by-user
On Oracle ERP application, non-utilisation of some ERP modules: Purchase
Order, Inventory & Training Admin due to absence of data.
CPM Review and revalidation of the Enterprise Scorecard by the
Governor/COG
eFASS.
Establishing communication link between CBN and NDIC and OFID’s
connection to the eFASS system.
Integration of the IDMS solution with MICR to enable the new redesigned
processes
Inability to sweep balances on regular basis via standing orders
Inability to detect errors in respect of returned unpaid instruments
Also the revaluation of FX by Reserve Management division of FOD.
July
2006:
Live run of T24, ERP and RTGS (net settlement) applications roll off in
Out Stations in phases (Phase1: Abeokuta, Ibadan and Ilorin on 24th July,
2006; Communication and Culture Change Team in collaboration with Project Team
conducted an awareness campaign in these branches to sensitise staff and
encourage their buy-in.
A help desk has commenced in Lagos for all banks and discount houses for e
FASS.
Conducted train-the –trainer training for DFD module of T24
Conducted regression testing for the Securities (GSS) module of the T24
application
Set up of training environment for RTGS (net settlement), migration of
Policy and Procedure Manual module on CPM. Concluded RTGS technical training
for the 1st batch of CBN staff. Continued the monitoring of live-run of the
RTGS net settlement module continued end-user training for rollout of T24 &
Oracle ERP applications to outstanding CBN branches. Concluded eFASS technical
training for CBN eFASS technical team
Live run of Instrument Processing module will be in Q2 2006 after
connectivity of all banks and discount houses to the CBN
Issues:
On T24 application, the systems’ inability to pass debit entries and the
setting
of head teller limits.
Inability to print Day-End journals by office instead of by-user
On Oracle ERP application, non-utilisation of some ERP modules: Purchase
Order, Inventory & Training Admin due to absence of data.
CPM Review and revalidation of the Enterprise Scorecard by the
Governor/COG
eFASS.
Establishing communication link between CBN and NDIC and OFID’s
connection to the eFASS system.
Integration of the IDMS solution with MICR to enable the new redesigned
processes
Inability to sweep balances on regular basis via standing orders
Inability to detect errors in respect of returned unpaid instruments
Also the revaluation of FX by Reserve Management division of FOD.
Agric Credit Guarantee Scheme:The Agricultural Credit Guarantee Scheme (ACGS) was established in 1977, under the management of the Central Bank of Nigeria. The scheme was designed to encourage banks to increase lending to the agricultural sector by providing guarantee against inherent risks.